How many ground rods needed for a temporary service at construction site?

1 answer

Answer

1052667

2026-03-01 02:50

+ Follow

The NEC makes no provision for using 1 ground rod even on a temporary service. According to the NEC you must use 2 ground rods. However in my area we are allowed by the local inspector to use just 1. Call your local inspector and see what he requires as he has the last Word on this.

ReportLike(0ShareFavorite