The question itself is not correct.
It should be what is the ultimate load carrying capacity of bored pile?
Ans: Ultimate load carrying capacity of pile could be determined be conducting load test.
Ultimate load:
The load at which the pile continuously settle.
or
the load at which settlement of the pile reaches 10 percent of its diameter