What is schedule variance in project management?

1 answer

Answer

1064148

2026-04-29 16:35

+ Follow

Schedule variance (SV) - This is the deviation of the performed schedule from the planned schedule in terms of cost. No confusion is allowed here because you already know that the schedule can be translated to cost. SV is calculated as the difference between EV and PV, as shown in the formula here:

SV = EV - PV