Do you have to pour all your concrete footings at once?

1 answer

Answer

1260880

2026-05-16 05:15

+ Follow

You should or at least each wall at the same time. You could pour it in sections as long as the rebar was joining each section. The problem would be at the joints. How to form up a section of the footing with the re bar in place. If the rebar is not tied together, the wall will move and never be what it should be.