Which Contract will require that the developer eat any additional expenses involved in the development of the system?

1 answer

Answer

1198301

2026-04-28 11:51

+ Follow

A Fixed-Price Contract typically requires that the developer absorb any additional expenses incurred during the development of the system. In this arrangement, the developer agrees to complete the project for a set amount, regardless of any unforeseen costs or changes that may arise. This places the financial risk on the developer, incentivizing them to manage their resources efficiently.