To determine the actual cost of work performed (ACWP), we can use the Cost Performance Index (CPI) formula, which is CPI = BCWP / ACWP. Rearranging gives us ACWP = BCWP / CPI. Substituting the given values, ACWP = 300 / 1.2, which results in an actual cost of 250. The Schedule Performance Index (SPI) is not fully provided, but if needed, it can be calculated using SPI = BCWP / BCWS.