The following data is received from your contractor Budgeted Cost of Work Performed (BCWP) 300 Cost Performance Index (CPI) 1.2 Budgeted Cost of Work Scheduled (BCWS) 400 Schedule Performance Index (S?

1 answer

Answer

1158492

2026-03-06 20:35

+ Follow

To determine the actual cost of work performed (ACWP), we can use the Cost Performance Index (CPI) formula, which is CPI = BCWP / ACWP. Rearranging gives us ACWP = BCWP / CPI. Substituting the given values, ACWP = 300 / 1.2, which results in an actual cost of 250. The Schedule Performance Index (SPI) is not fully provided, but if needed, it can be calculated using SPI = BCWP / BCWS.