How are Work Breakdown Structure and project networks linked?

1 answer

Answer

1280945

2026-04-28 23:30

+ Follow

WBS and project networks are linked because project networks are developed from the WBS. Work packages from the WBS are used to build the activities found in the project network. Integration of the WBS and project network is crucial to effective project management. The project manager must be careful to guarantee continuity by having some people who defined the WBS and work packages developed the network activities.