Input : 1. Thickness of plastering 12mm (0.012m). 2. Cement sand ratio 1:6
Suppose we require to plaster 100sqm
Then 100x0.012=1.2m3 of mortar is required
For 1:6 ratio,
Cement requirement will be= 1.2 x 1/7 (one part of cement in mortar) = 0.1714m3 cement,
Since cement goes in the voids of sand we nead 20% extra material = 1.20 x 0.1714 = 0.2056 cum.
Now add 20% extra to cover uneven surface of brick work = 1.2 x 0.2056 = 0.2468 cu. m of cement.
Now for 50 kg of cement = 0.0345cum, therefore = 0.2468 / 0.0345 = 7 bag of cement.
Sandrequirement will be= 1.2 x 6/7 (sixth part of sand in mortar) = 1.0285 m3 sand
Now add 20% extra to cover uneven surface of brick work = 1.2 x
1.0285
= 1.2343 cu. m of sand.
Convert sand in MT multiply is by 1.602 (specific gravity) 1.2343 x 1.602 = 1.9773 MT