Why in primavera P6 schedule the total float for all activitity is negative?

1 answer

Answer

1106347

2026-07-22 03:35

+ Follow

one possible reason is that you dont have the correct dates in the project view->dates. try matching the project planned start date with the activity that kicks the programme off, and match the project must finish by date to the final activity in your programme.