TRUE OR FALSE - If a contractor makes a timely request for a debriefing and you do not accommodate at that point your inaction doesn and acirc and 128 and 153t extend the contractor and acirc and 128?

1 answer

Answer

1160902

2026-07-27 13:45

+ Follow

TRUE. If a contractor makes a timely request for a debriefing and the contracting officer does not accommodate that request, the inaction does not extend the contractor's time to file a protest. The contractor is still bound by the original deadlines for filing a protest, regardless of the debriefing request.